Reader question: Why widen U.S. 20 before more of I-90?

October 15th, 2009 at 03:03pm Thomas V. Bona

Passenger Seat regular Sally Hanks asked a good question that deserved its own post.

Speaking of freeways: Although I would welcome the widening of U.S. 20 from I-39 to IL-2, I question the prioritization. If they come up with an assesment that says it needs it, and/or the funds are available, why don’t they direct those funds to widen I-90 between Elgin and Rockford? No assesment needed there!

Thanks for the question. A few things:

  1. Remember, I-90 between Elgin and Rockford is the Illinois Tollway, so all widening projects there are paid for by tolls not by state construction funds. By statute, IDOT can’t send its money, which comes from fuel taxes, registration fees and other funds, to tollway projects.
  2. Even if they could, Elgin to Rockford is much farther than the U.S. 20 project. They couldn’t get very far in that widening if they put this money to it.
  3. It’s not that the assessment is to determine if the project is needed - they’ve already determined it is - it’s the necessary environmental study to see what alignment the road should be in, and whether widening can be done without too many negative impacts.
  4. Actually, from a pure numbers point of view, the 20 project does pretty well vs. the tollway. First of all, there’s a separate project to widen the bypass between the Cherry Valley interchange and where I-39 heads south. That presumably is a higher priority, and would cause a bit of a choke point on U.S. 20 if more of the bypass isn’t widened. Also, while traffic on the bypass is less the Tollway, it’s not tons less. The portion where U.S. 20 and I-39 share actually has higher traffic than the tollway does for a good chunk of the Elgin-Rockford stretch; while the rest of the bypass  to be widened has perhaps 5 to 25 percent less traffic, according to Getting Around Illinois.

But I think point number 1 is the biggest key. Thanks for the question!

Entry Filed under: Uncategorized

2 Comments Add your own

  • 1. carl  |  October 15th, 2009 at 3:33 pm

    I suspect this is because the Rock River bridges need to be replaced soon, one of crossovers is already in place. The question becomes they might as well be widen to 3 ways in each direction while the bridges are being replaced, even if the widening is 10 years off.

    Hopefully that would also mean we would only have 1 year of the bridges being 1 lane in each direction as they could replace 1 bridge and have it wide enough to take 4 lanes of traffic the following year when the other bridge would be replaced.

    I can see the bypass needing widening from I39 to Main Street west of Main street I am not sure of in the next 10 years. And as Thomas mentioned the section between I90 and I39 is already in the works.

  • 2. Thomas V. Bona  |  October 15th, 2009 at 3:36 pm

    Carl,

    Yes - because the bridges have to be replaced in about three years, they want to know how wide to make them. So they’re studying the road widening now.

    U.S. 20 from 39-Ill 2 isn’t in the five year plan, so it’s 6+ years away. We all know how long it takes to get projects on the schedule, so who knows WHEN it’ll happen, really.

Leave a Comment

Required

Required, hidden

Security Code:

Some HTML allowed:
<a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <code> <em> <i> <strike> <strong>

Trackback this post  |  Subscribe to the comments via RSS Feed


Search

Latest Posts

Calendar

October 2009
M T W T F S S
« Sep   Nov »
 1234
567891011
12131415161718
19202122232425
262728293031  

Posts by Month


Most Recent Posts

Posts by Category

Syndication